Edward M. Bradfuhrer PE
Project Manager/Modeling/Linear Assessments

Location  Experience
Niagara Falls, New York USA  17 years

Qualifications/Accreditations
– BS, Environmental Engineering, 2009

Memberships
– Registered Professional Engineer, New York
– New York water Environmental Association
– American Society of Civil Engineers

Relevant experience summary
 Ed is a project manager and project engineer who has extensive experience modeling complex hydraulic
 structures starting with his work in the Buffalo, NY and Niagara Falls sewer systems. These combined sewer
 communities contain complex flow control structures that are meant to limit water levels and protect property.
 This experience led Ed to start GHD’s computational fluid dynamics modeling group in North America. He is
 always interested in ways to improve project outcomes and has piloted modeling software like Optimatics and
 Infoworks ICM cloud modeling capabilities to optimize projects, reduce delivery time, and control costs.

SSES Re-Evaluation  SWMM Model Development
Project Manager | Town of West Seneca  Technical Advisor |
| West Seneca, NY, USA  Niagara County Sewer District No. 1 |
  Niagara County, NY, USA
Led pilot testing of Optimatics for use in an
optimization analysis of a sewer rehabilitation program  Directed the development of a new sewer system
meant to reduce system inflow and mitigate sanitary  model for Niagara County Sewer District No. 1, which
sewer overflows. The software used a genetic  will be used to assist with locating flow restrictions in
algorithm to game sewer lining, lateral lining, off-line  the system and assist with accommodating future
storage, and added system capacity to determine a  development. Determined the location of flowmeter
program that could improve outcomes at a lower cost  installation, analyzed flowmeter data, trained junior
than the current plan. The software helped identify a  personnel in calibrating sewer models and geographic
recommended program that can better reduce sewer  information systems, and reviewed model calibration.
overflows at half the cost of the current program.
  West Side Interceptor Evaluation
Plant 5 Flowmetering  Modeler and Technical Advisor |
Project Manager | Town of West Seneca  Town of Amherst | Amherst, NY, USA
| West Seneca, NY, USA  Led a team of engineers and modelers who performed
Updated plans and specifications that were produced  a study on the feasibility of installing a relief sewer for
for regulatory review so that a new flowmeter and  the West Side interceptor in Amherst, NY. Options
overflow control structure be bid and constructed.  evaluated included gravity conveyance, pumping
Managed a project team that provided bidding,  station and forcemain, and green infrastructure.
construction administration, controls integration, and  Probable project costs, preliminary layouts, ecological
startup assistance. Construction of the project  impacts, and non-monetary factors were evaluated for
ultimately reduced sanitary sewer overflows in the  each alternative. A pumping station and forcemain was
system and improved data accuracy, which reduced  determined to be the most feasible option for sewer
recurring treatment costs paid to the City of Buffalo.  relief and is anticipated to be implemented by the
  Town.