Our response  –  Model Calibration: Using data collected during
  flowmetering in 2023, GHD calibrated the model
The Town expressed several concerns with
  using a long-term simulation of the dataset. Results
upcoming requirements of the 2012 Order, which
  of the I/I Study suggested that the relationship
included updating the Long Term Control Plan in the
  between rainfall and I/I is linear, which indicated that
required time. Further discussions with the NYSDEC
  the RTK unit hydrograph model was sufficient to
led to developing a revised approach to I/I reduction
  achieve a satisfactory simulation. This was
and SSO abatement and negotiating modifications to
  confirmed by satisfactory calibration metrics for ran
the Order to include a phased approach to
  events in the simulation. The model is currently
addressing I/I and SSOs moving forward. GHD was
  being used for planning and reporting.
engaged with the Town throughout every step of this
process, including preparing the first modified Order  –  Engineering Report: Results were presented in a
deliverable, the Sewer System Inflow and Infiltration  model calibration report that followed the outline in
Work Plan that outlined the framework for the  the approved Model Work Plan. The report
proposed flow monitoring and system-wide I/I Study.  described calibration methods, general statistics,
The I/I Study was submitted to NYSDEC on  and included storm hydrographs and scattergraphs
April 17, 2024 and outlined flow and rain monitoring  showing the correlation between model results and
data collection for both the I/I Study and the sewer  measured data.
system model update/calibration requirements
concurrently, quantified I/I in the study subbasins,
  The impact
and validated flow data, which allowed the Town to  Creation of the I/I Work Plan and calibrated model
be more efficient with its limited resources.  improved the Town’s ability to plan system assessment
  and rehabilitation. The improved model increased the
The Sewer System Model Work Plan described a
  accuracy of overflow predictions and is anticipated to
general plan for constructing a new sanitary sewer
  contribute to optimized sewer system upgrades.
model, its proposed uses, and a schedule for
submission of a model calibration report. The Model
Work Plan was approved by the NYSDEC on
September 27, 2023. While the Model Work Plan
was under review by the NYSDEC, the Town was
performing field investigations to update the sewer
GIS dataset in anticipation of the recalibration work.
This updated dataset was used as the basis for the
updated model, which was due on
November 1, 2024.
Model calibration included the following tasks:
–  Model Update: GHD created an “all pipe” model
  using the updated GIS dataset provided by the
  Town. This dataset was imported directly into
  Infoworks ICM and evaluated for missing
  information, pipes sloping in the wrong
  direction, and other items that can lead to
  inaccurate output. Pump stations within the
  Town were modeled based on information
  provided in record drawings and operational
  data.