Under our initial authorization, GHD prepared a Map,  The impact
Plan and Report for the Phase 16 extension,  Upon construction completion, the Town of Royalton will
completed the SEQR and SHPO coordinated  have increased public water supply for its residents.
reviews, along with surveying and a wetlands  Residents along the project area will experience
delineation which were provided by outside  improved capacity, reliability, and pressure.
consultants.
GHD subsequently provided detailed design, which
included the following in each area:
–  Approximately 15,620 LF (2.95 miles) of 8-inch
  polyvinyl chloride (PVC) pipe, valves, services,
  fire hydrants, and associated appurtenances on
  Ditch Road and Griswold Street between Foote
  Road and Lewiston Road (NYS Route 77).
–  Approximately 4,320 LF (0.82 miles) of 8-inch
  PVC pipe, valves, services, fire hydrants, and
  associated appurtenances on Akron Road from
  Bulmore Road to NYS Route 93.
–  Approximately 5,700 LF (1.08 miles) of 8-inch
  PVC pipe, valves, services, fire hydrants, and
  associated appurtenances on Akron Road from
  NYS Route 93 to Grove Road.
GHD coordinated with various local, county and state
agencies, and utilities to obtain permits and land use
agreements for the project, and is currently providing
construction contract administration and resident
inspection.