Draft Colden Chapter #101 Battery Energy Storage Systems
  Planning Board Revision #15 (dated 8/10/26)

 the Town of Colden Planning Board, the Colden’s Town Engineer, or the Colden Town Board before
 an application is deemed complete and ready for ultimate action by the Town Board. Any site plan
 application shall include, as a minimum, the following information:
  1. Property lines and physical features, including roads, for the project site on a survey produced,
  signed and sealed, by a licensed NYS licensed Registered Professional Land Surveyor (RPLS).
  2. Proposed changes to the landscape of the site, grading, vegetation clearing and planting,
  exterior lighting, and screening vegetation or structures.
  3. A three-line electrical diagram detailing the battery energy storage system layout, associated
  components, and electrical interconnection methods, with all National Electrical Code
  compliant disconnects and over current devices.
  4. A preliminary equipment specification sheet that documents the proposed battery energy
  storage system components, inverters and associated electrical equipment that are to be
  installed. A final equipment specification sheet shall be submitted prior to the issuance of
  building permit.
  5. Name, address, and contact information of proposed or potential system installer and the
  owner and/or operator of the battery energy storage system. Such information of the final
  system installer shall be submitted prior to the issuance of building permit.
  6. Name, address, phone number, and signature of the project Applicant, as well as all the
  property owners, demonstrating their consent to the application and the use of the property for
  the battery energy storage system.
  7. Zoning district designation for the parcel(s) of land comprising the project site.

  8. Commissioning Plan. Such plan shall document and verify that the system and its associated
  controls and safety systems are in proper working condition per requirements set forth in the
  Uniform Code. Where commissioning is required by the Uniform Code, Battery energy storage
  system commissioning shall be conducted by a New York State (NYS) Licensed Professional
  Engineer (P.E.) after the installation is complete but prior to final inspection and approval. A
  corrective action plan shall be developed for any open or continuing issues that are allowed to be
  continued after commissioning. A report describing the results of the system commissioning and
  including the results of the initial acceptance testing required in the Uniform Code shall be provided
  to the Colden Code Enforcement Department and Colden Planning Board for advisory
  recommendations and conditions prior to action by the Colden Town Board prior to final
  inspection and approval. The report shall be submitted to the Town and an identical copy
  maintained at an approved on-site location.
  9. Fire Safety Compliance Plan. Such plan shall document and verify that the system and its
  associated controls and safety systems are in compliance with the Uniform Code. The Plan
  should clearly indicate compliance with all provision of the NFPA, including methods and
  means for the supply of adequate water for potential fire suppression of the structure itself,
  adjoining equipment, and other combustible materials such as grasslands, forested areas,
  and non-battery materials needed by Colden First Responders and the Colden Fire
  Company. Full compliance with the requirements, procedures, and documentation in
  accordance with NYS Uniform Fire NFPA 855 shall be included in the plan.
  10. Operation and Maintenance Manual. Such plan shall describe continuing battery
  energy storage system maintenance and property upkeep, as well as design,
  construction, installation, testing and commissioning information and shall meet all
  requirements set forth in the Uniform Code.

TOWN OF COLDEN – BATTERY ENERGY STORAGE SYSTEMS  11