Eden Central School District – Capital Project Management (2024M-83)

Government
Eden Central School District
Posted by publisher
Oct 4, 2024
Kind
State audit
Topics
Audits and oversight, Budget and taxes, Roads and traffic

Publisher's summary

Determine whether the Eden Central School District (District) Board of Education (Board) and District officials provided sufficient oversight of and managed the District’s 2022 capital project (project) in a transparent manner.

Original document

Text · page 10 of 17

The Superintendent told us that officials did not obtain prior SED approval because the work was within
the project’s scope, and it would delay the project if the District had to wait for approval. However, the
work was not within the project’s scope. Also, the Superintendent should have consulted with SED,
verbally or through written communication, before completing large change orders to ensure that the
work would be eligible for building aid.

Furthermore, work associated with 10 change orders totaling $226,695 was completed on average 11
days before District officials approved the change orders. The Superintendent told us that the work was
done before being approved because vendors did not submit their quotes in a timely manner. However,
appropriate approvals should have been obtained before the work was completed, as required, to
ensure the scope of the work was appropriate and met District needs. Moreover, if the Director solicited
quotes from other vendors, rather than only the vendors already working on the project, the competition
may have resulted in more timely quote submissions and possibly even lower prices.

In addition, officials submitted change orders to SED on average 10 days after the Superintendent
approved them. The Director told us that the District relied on the architect to submit the change orders
in a timely manner once they were approved by the Superintendent. However, the Superintendent was
responsible for ensuring that the architect submitted change order applications in a timely manner.

Because the Superintendent did not ensure that proper change order approvals were obtained before
the work was completed, he allowed the change order approval process to be circumvented and risked
having building aid withheld.

Officials Did Not Seek Competition for Professional Services
While the District’s purchasing policy and procurement procedures require District officials to use
a request for proposals (RFP) process when contracting for professional services, the policy and
procedures do not state the dollar threshold for using the RFP process, who is responsible for
requesting proposals, how many proposals should be obtained, what selection process should be used
or how RFP actions should be documented.

District officials did not seek competition by requesting proposals for five professional services totaling
more than $2 million. Of that amount, nearly $1 million was for architectural services and $940,000 for
construction management services. The three remaining professional services totaling approximately
$128,000 were for legal fees, bond service and consulting services.

The Director told us that the architect, construction management and bond service contracts were
awarded before she was employed with the District. She also said that the District had been contracting
with the architectural and construction management firms for many years. In addition, she told us that,
at the Board’s reorganizational meeting, it approved the attorney who provided the legal services.
However, this approval was for general legal matters and not specifically related to the project, which
had a separate contract. Furthermore, the Director told us that the Board approved the consulting
services at a special Board meeting. However, this approval was for a general financial consulting
service unrelated to the project.

8  Of f ic e of t he New York State Comptroller