Report Highlights
 Eden Central School District

Audit Objective
  Audit Period
Determine whether the Eden Central School
District (District) Board of Education (Board) and  October 14, 2020 – March 15, 2024
District officials provided sufficient oversight of and
managed the District’s 2022 capital project (project)  Background
in a transparent manner.
  The District serves the Towns of Boston,
  Concord, Eden, Evans and North Collins
Key Findings  in Erie County.

The Board and District officials did not provide  The Board is responsible for managing
adequate oversight or manage the project in a  and controlling the District’s financial and
transparent manner. We determined that:  educational affairs. The Superintendent
  l $545,538 of additional work was not included
  of Schools (Superintendent) is the
  in the project proposition or subsequently  District’s chief executive officer and is
  communicated to voters. As a result, voters  responsible for the District’s day-to-day
  were not afforded the opportunity to approve or  management.
  reject the additional work.  The Director of Finance (Director)
  l Officials did not seek competition for $3.2  is responsible for administering and
  million paid for change order work and  supervising the District’s financial
  professional services. Therefore, officials may  activities. The Superintendent of
  have paid more than if the work was awarded  Buildings and Grounds (Building
  through a competitive process.  Superintendent) is responsible for
  directing and supervising the District’s
  l The Board did not review and approve any of
  facilities operations, including capital
  the 108 project change orders totaling $1.4
  projects and the construction manager.
  million, and officials did not submit change
  However, the Board is ultimately
  orders to the New York State Education
  responsible for overseeing and managing
  Department (SED) in a timely manner for
  the District’s capital projects.
  approval.
  Quick Facts
Recommendations  Project Budget  $15.9 million

The audit report includes eight recommendations  Original Contracts  $14.6 million

to help District officials improve their oversight and  Change Orders (Net)  $1.2 million
management of capital projects.  Added Work Not Included
  $545,538
  in Original Plans
District officials generally agreed with our findings
and recommendations and indicated they would
take corrective action. Appendix B includes our comment on an issue raised in
the District’s response.

  Of f ic e of t he New York State Comptroller  1