Southtowns Record

10/13/26 Board Packet

Government
Village of Gowanda
Board
Village Board
Meeting
Oct 13, 2026
Kind
Agenda packet
Topics
Audits and oversight, Water, sewer and drainage, Public safety, Budget and taxes, Roads and traffic, Zoning and land use, Parks and recreation

Original document

Same meeting

Text · page 70 of 90

Read the whole document on one page (all 90 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

Change Request  1
September 2, 2026

Current Budget Status
Total contract breakdown is provided below.

  Drilling Subcontractor  $  19,750.00
  Laboratory Subcontractor  $  38,200.00
  Data Usability Report  $  6,506.00
  C&S Expenses & Equipment  §  2,800.00
  C&S Labor  $  26,900.00
  Total Contract Amount  $  94,150.00

  Active Budget:  $  94,150.00
  Previous Invoices:  $  80,027.50
  Remaining:  $  © 14,122.50

Change Request #1:  Additional Groundwater Weil, Laboratory Testing, and Analysis
At this time the original budget has been used; however, additional fees have been incurred. Additional or out-
of-scope work includes the following:

e  The advancement of a fourth groundwater  monitoring well at the site to investigate the discovered
  petroleum impacts.
e  Laboratory testing and analysis of the additional groundwater sample.
e  Miscellaneous project management and coordination with New York State Department of Environmental
  Conservation.

Total for Change Request #1  $  = 2,472.45

New Budget Status:
  Net Total ofall Change Requests  $  2,472.45
  Active Budget Amount  $94,150.00  :
  Revised Active Budget Amount  $  96,622.45

C&S Companies | Change Reque