**A reduction in fee can be provided for the following services: • $3,500 if municipality can provide permit/construction information for each property in boundary expansions and new Historic District in requested format. • $3,000 if municipality can provide final mapping for contributing and non- contributing properties in proposed districts • Total fee after reduction: $32,500 Proposed Fee Schedule for Intensive- Level Survey: 15% Retainer 20% Upon completion of survey 35% Submission of Draft Survey to Client and SHPO 15% Upon formal submission of Survey to Client and SHPO 10% Upon final approval by SHPO. 5% Upon completion of all public meetings. Estimated Project Timeline Kickoff meeting Week 1 Survey Weeks 2-12 Survey documentation Weeks 2-12 Survey Draft preparation Weeks 12-38 Survey Draft Revisions Weeks 38-44 Final Survey Submission Week 45 Community Meetings Various Total time: 45 weeks 8