Project Name: Bridge NY (Culvert) Project  Greymont Avenue over Ebenezer Brook
  Project Number:  PIN 5765.16
  Bid Date: 01/29/2026

  Contractors (Bid Order)
  BIDS
  Purchased Plans & Specs
RANK  Engineers Estimate  $  372,510.58
 1  Union Concrete & Construction Corp.  $  330,151.00  88.63%
 2  Matt Kolo Excavating  $  352,347.73  94.59%
 3  Huntington Valley Construction  $  385,399.00  103.46%
 4  E&R General Construction Inc.  $  434,545.00  116.65%
 5  Note: Bids in Red are corrected  0.00%
 6  $  -  0.00%
 7  $  -  0.00%
 8  $  -  0.00%
 9  $  -  0.00%
 10  $  -  0.00%