TO:  Honorable Town Board
FROM:  Jason Foote, Town Engineer
DATE:  April 13, 2026
SUBJECT:  Town Engineer re Engineering Planning Grant - Local Share
  Resolution

Requested Action:  The Town of West Seneca applied for an Engineering Planning Grant
  (EPG) in 2025 and was successful in receiving a grant in the amount
  of $100,000. As part of the grant requirements, the Town is
  responsible for a minimum 20% local share contribution toward the
  project. A letter which indicated that the Town was willing to commit to
  the minimum 20% local share was submitted with the original grant
  application, but nothing formal was ever fully adopted.

  At that time, we estimated the total project cost to be $165,000, which
  would have made the Town share $65,000. However, the proposal
  that the Town awarded in February 2026 to GHD was for $237,800,
  which makes the Town’s share $137,800 instead of $65,000. The
  local share is expected to be funded from available Sewer funds.

  Therefore, we are requesting the Town pass the attached suggested
  resolution at the April 13, 2026, Town Board Meeting.

RESOLUTION:  WHEREAS, the Town of West Seneca previously submitted an
  application to the New York State Environmental Facilities Corporation
  (NYS EFC) for an Engineering Planning Grant (EPG) to complete a
  sanitary sewer system evaluation, including flow monitoring, hydraulic
  analysis, and development of recommendations to reduce inflow and
  infiltration and improve system performance; and

  WHEREAS, the Town was awarded an Engineering Planning Grant in
  2025 in the amount of $100,000; and

  WHEREAS, the total estimated cost of the engineering planning study
  is $237,800; and

  WHEREAS, the EPG program requires a minimum local match of at
  least 20% and that any project costs exceeding the grant award are
  the responsibility of the municipality;

  NOW, THEREFORE, BE IT RESOLVED that the Town of West