Water, sewer and drainage, Zoning and land use, Public safety, Budget and taxes, Parks and recreation, Roads and traffic, Audits and oversight, Moratoriums, Energy and data center siting, Short-term rentals, Housing

Original document

Same meeting

Text · page 62 of 240

Read the whole document on one page (all 240 pages, each with its own heading)

b) The monitoring locations inspection and sampling program (MCM 3: Illicit Discharge
  Detection and Elimination) includes all Village of East Aurora municipal facilities.

  c) Comprehensive Site Assessments
  i) Once every five (5) years following the most recent assessment, the Village of East
  Aurora will complete a comprehensive site assessment for each high priority
  municipal facility as identified in the inventory using the Municipal Facility
  Assessment Form (Appendix J) or an equivalent form containing the same
  information, and document it in the municipal facility specific SWPPP and SWMP Plan
  that:
  (a) The municipal facility is in compliance with the terms and conditions of the
  NYSDEC SPDES General Permit for Stormwater Discharges from Municipal
  Separate Storm Sewer Systems (GP-0-24-001;

  (b) Deficiencies were identified and all reasonable steps taken to minimize
  any discharge in violation of the permit, which has a reasonable likelihood of
  adversely affecting human health or the environment;
  (i) Within twenty-four (24) hours, the MS4 Operator must prepare a
  schedule that includes corrective actions and specific interim
  milestones to be implemented until the corrective action is
  implemented; or

  (c) Deficiencies were identified and all reasonable steps taken to minimize any
  discharge in violation of the permit, which does not have a reasonable
  likelihood of adversely affecting human health or the environment;
  (i) Within seven (7) days, the MS4 Operator must prepare a
  schedule that includes corrective actions and specific interim
  milestones to be implemented until the corrective action is
  implemented.

e. Low Priority Municipal Facility Requirements
i. The MS4 Operator must identify procedures outlining BMPs for the types of activities that occur at
the low priority municipal facilities. A municipal facility specific SWPPP is not required.

ii. Municipal Facility Assessments
  a) Low priority municipal facilities are not required to conduct wet weather visual
  monitoring.

  b) The monitoring locations inspection and sampling program is conducted at the municipal
  facility.

  c) Comprehensive Site Assessments
  i) Once every five (5) years following the most recent assessment, the Village of East
  Aurora will complete a comprehensive site assessment for each low priority
  municipal facility as identified in the inventory using the Municipal Facility