Town Board of the Town of Hamburg October 19, 2026 Meeting 4.29. Senior & Community Center Change Orders WHEREAS, as the Senior & Community Center project progresses, the contractors have run into challenges, and the Town has made requests for revisions on the project; and WHEREAS, the General Contractor, Resetarits, and the Electrical Contractor, CIR, has provided change orders to cover the cost impacts of these revisions as part of the project and the change orders have been reviewed by the Town Engineer and town’s construction manager; and WHEREAS, the attached general change orders cover the following items: · Revisions to the septic system to relocate following changes to the stormwater management system, to move structures away from the rear of the building by the patio, and add a new structure and pump due to increase in depth = $37,887.90 · Credit to the Town for waterline no longer required = Minus $11,479.00 WHEREAS, the attached electrical change orders cover the following items: · Revisions to kitchen, fitness room, reception desk and classroom electrical. Kitchen and fitness revisions per the equipment layouts approved by the County Health Department. Reception desk per workstation and IT. Classroom revision around new cabinets = $10,912.43 · Revisions to the electrical to add additional poles and lights to the existing parking lot, to move the existing overhead wires to underground duct bank, to connect the hotbox power needed, and to extend the connection to the septic system = $242,771.97 THEREFORE BE IT RESOLVED, that the Town Board hereby authorizes the Supervisor to sign the attached change orders and approves a budget amendment increase of $280,093.30 from the following accounts: INCREASE: A000.0000.0599.0000 (General Fund Appropriated Fund Balance) by $280,093.30 INCREASE: A000.9950.0975.0004 (Interfund Transfers Transfer to Capital) by $280,093.30 INCREASE: H119.0000.5031.0000 (Capital Construction) by $280,093.30 INCREASE: H119.7187.0281.0004 (Interfund Transfers Transfer to Capital) by $280,093.30 ATTACHMENTS: RFC#18R1 Sanitary Revisions.pdf RFC#17 Credit for RFC#07.pdf CIR-COR #8 - Kitchen & Reception Desk Power Modifications.pdf CIR-COR #9r1 - RFP-005 Underground Electric Modifications.pdf 144