ELECTRIC SERVICE PROPOSAL WR#31203402

  Town of Hamburg
  2800 Lakeview Rd
  Hamburg, NY 14075

Service Work Request:  31203402

Electrical Contractor:  Stenzel Electric

Customer’s Contribution:  $10,541.00

Billing Party:  Town of Hamburg

Customer’s  ➢ Return signed Proposal cover letter, if accepted
Responsibilities:  ➢ Provide all necessary right-of-way easements
  ➢ Notify National Grid if any changes in the Billing Party
  occur
  ➢ Payment in full, upon receipt of invoice
  ➢ Provide copy of Tax-Exempt Certificate (if applicable)
  ➢ Adherence to applicable Electric Service bulletin(s)
  Electric Specifications (site.com)
National Grid  Installing new pole/transformer, replacing 2 poles and
Responsibilities:  installing 200’ OH single phase primary wire.
Construction Lead Time:  Approximately 4-6 weeks will be necessary for construction.
  Upon receipt of payments, permits, right-of-way and the signed
  Agreement, this project will be added to National Grid’s
  construction schedule.

  Note: Payment must be made upon receipt of invoice. The
  correct mailing address for payments will be noted on the
  invoice you receive.
Customer  If a progress report is needed during construction, including the
Communications Update:  expected date for the Owners project completion, the expected
  completion date for the utility’s work, and confirmation of the
  expected date for the service connection of permanent power,
  please contact the Company Job Owner at the number listed
  below.
Remarks:  This Proposal is based upon projected cost and rate schedule
  provisions in effect at the date of this proposal and will be
  withdrawn if not accepted within 90 days of the date of this
  Proposal.

  This proposal and all attached documentation are proprietary
  property of National Grid and can only be used for its intended
  purpose and shall not otherwise be disclosed.