4.0  CONSTRUCTION SEQUENCE
 This project has not received written approval from the Town of West Seneca allowing the disturbance
 of more than five acres of land at any one time. Therefore, if the Contractor’s construction sequence
 requires the disturbance of more than five acres at any one time, written approval must be obtained
 from written approval from the Town of West Seneca prior to disturbing more than five acres at once.

 The “Erosion and Sediment Control Plan” and the “Erosion and Sediment Control Plan Prior to
 Construction” in the accompanying drawings and waiver request identifies the major construction
 activities that are the subject of this SWPPP. The order (or sequence) in which the major activities are
 expected to begin is presented on the accompanying drawings, though each activity will not necessarily
 be completed before the next begins. In addition, these activities could occur in a different order if
 necessary to maintain adequate erosion and sediment control. If this is the case, the contractor shall
 notify the Owner’s/Operator’s Engineer overseeing the implementation of the SWPPP.

 The Contractor will be responsible for implementing the erosion and sediment control measures
 identified on the plans. The Contractor may designate these tasks to certain subcontractors as they
 see fit, but the ultimate responsibility for implementing these controls and ensuring their proper
 function remains with the Contractor.

 In accordance with Part III.B.c.iv. a phasing plan for the project and sequencing plans for all phases
 have been provided. The plans address clearing and grubbing, excavation and grading, utility and
 infrastructure installation, final stabilization, and any other construction activity at the site that will
 result in soil disturbance. Refer to the plans for further information on the project phasing and
 sequencing.

 5.0  CONSTRUCTION-PHASE POLLUTION CONTROL
 The SWPPP and accompanying plans identify the temporary and permanent erosion and sediment
 control measures that have been incorporated into the design of this project. These measures will be
 implemented during construction, to minimize soil erosion and control sediment transport off-site, and
 after construction, to control the quality and quantity of stormwater runoff from the developed site.

 Erosion control measures, designed to minimize soil loss, and sediment control measures, intended
 to retain eroded soil and prevent it from reaching water bodies or adjoining properties, have been
 developed in accordance with the following documents:
  •  NYSDEC SPDES General Permit for Stormwater Discharges From Construction Activity, Permit
  No. GP-0-25-001 (effective January 29, 2025 through January 28, 2030)
  •  New York State Standards and Specifications for Erosion and Sediment Control, NYSDEC
  (November 2016)

 The SWPPP and accompanying plans outline the construction scheduling for implementing the erosion
 and sediment control measures. These documents include limitations on the duration of soil exposure,
 criteria and specifications for placement and installation of the erosion and sediment control
 measures, a maintenance schedule, and specifications for the implementation of erosion and
 sediment control practices and procedures.

 Temporary and permanent erosion and sediment control measures that shall be applied during
 construction generally include: