1. Minimizing soil erosion and sedimentation by stabilization of disturbed areas and by removing
  sediment from construction site discharges.
  2. Preservation of existing vegetation to the greatest extent practical. Following the completion
  of construction activities in any portion of the site, permanent vegetation shall be established
  on all exposed soils.
  3. Site preparation activities to minimize the area and duration of soil disruption.
  4. Establishment of permanent traffic corridors to ensure that “routes of convenience” are
  avoided.

 5.1 Temporary Erosion and Sediment Control Measures

 The temporary erosion and sediment control measures described in the following sections are
 included as part of the construction documents.

 5.1.1  Stabilized Construction Access
 Prior to construction, stabilized construction access(es) will be installed, per accompanying plans, to
 reduce the tracking of sediment onto public roadways.

 Construction traffic must enter and exit the site at the stabilized construction access(es). The intent is
 to trap dust and mud that would otherwise be carried off-site by construction traffic.

 The access(es) shall be maintained in a condition, which will control tracking of sediment onto public
 rights-of-way or streets. When necessary, additional aggregate will be placed atop the filter fabric to
 assure the minimum thickness is maintained. All sediment and/or soil spilled, dropped, or washed
 onto public rights-of-way must be removed immediately. Periodic inspection and needed maintenance
 shall be provided after each substantial rainfall event.

 5.1.2  Dust Control
 Water trucks shall be used as needed during construction to reduce dust generated on-site. Dust
 control must be provided by the Contractor(s) to a degree that is acceptable to the Owner, and in
 compliance with the applicable local and state dust control requirements.

 5.1.3  Temporary Soil Stockpile
 Materials, such as topsoil, will be temporarily stockpiled (if necessary) on the site during the
 construction process. Stockpiles shall be located in an area away from storm drainage, water bodies
 and/or courses, and will be properly protected from erosion by a surrounding silt fence barrier.

 5.1.4  Silt Fencing
 Prior to the initiation of and during construction activities, a geotextile filter fabric (or silt fence) will be
 established downgradient of all disturbed areas. These barriers may extend into non-impact areas to
 provide adequate protection of adjacent lands.

 Clearing and grubbing will be performed only as necessary for the installation of the sediment control
 barrier. To facilitate effectiveness of the silt fencing, daily inspections and inspections immediately
 after significant storm events will be performed by the Contractor(s). Maintenance of the fence will be
 performed as needed.

Stormwater Pollution Prevention Plan
  Page 15
2241067