control system performance as well as particular details of individual system components. Additional
 factors should be considered as appropriate to the circumstances.
  1. Locations where vehicles enter and exit the site must be inspected for evidence of off-site
  sediment tracking. A stabilized construction access will be constructed where vehicles enter
  and exit. This access will be maintained or supplemented as necessary to prevent sediment
  from leaving the site on vehicles.
  2. Sediment barriers must be inspected and, if necessary, they must be enlarged or cleaned in
  order to provide additional capacity. All material from behind sediment barriers will be
  stockpiled on the up slope side. Additional sediment barriers must be constructed as needed.
  3. Inspections will evaluate disturbed areas and areas used for storing materials that are exposed
  to rainfall for evidence of, or the potential for, pollutants entering the drainage system. If
  necessary, the materials must be covered or original covers must be repaired or
  supplemented. Also, protective berms must be constructed, if needed, in order to contain
  runoff from material storage areas.
  4. Grassed areas will be inspected to confirm that a healthy stand of grass is maintained. The
  site has achieved final stabilization once all areas are covered with building foundation or
  pavement, or have a stand of grass with at least 80 percent density. The density of 80 percent
  or greater must be maintained to be considered as stabilized. Areas must be watered,
  fertilized, and reseeded as needed to achieve this goal.
  5. All discharge points must be inspected to determine whether erosion control measures are
  effective in preventing significant impacts to receiving waters.

 The inspection reports must be completed entirely and additional remarks should be included if
 needed to fully describe a situation. An important aspect of the inspection report is the description of
 additional measures that need to be taken to enhance plan effectiveness. The inspection report must
 identify whether the site was in compliance with the SWPPP at the time of inspection and specifically
 identify all incidents of non-compliance.

 Within one (1) business day of the completion of an inspection, the Qualified Inspector/Qualified
 Professional shall notify the Owner/Operator and appropriate contractor or subcontractor of any
 corrective actions that need to be taken. For corrective actions not requiring engineering design, the
 contractor must begin implementing corrective actions within one business day and complete the
 corrective actions within five business days. For corrective actions requiring engineering design, the
 engineering design process must begin within five business days and the contractor must complete
 the corrective action in a reasonable time frame but no later than 60 calendar days.

 In addition to the inspections performed by the Qualified Inspector/Qualified Professional, the
 Contractor shall perform routine inspections that include a visual check of all erosion and sediment
 control measures. All inspections and maintenance shall be performed in accordance with the
 inspection and maintenance schedule provided on the accompanying plans. Sediment removed from
 erosion and sediment control measures will be exported from the site, stockpiled for later use, or used
 immediately for general non-structural fill.

 It is the responsibility of the general contractor to assure the adequacy of site pollutant discharge
 controls. Actual physical site conditions or contractor practices could make it necessary to install more
 structural controls than are shown on the accompanying plans. (For example, localized concentrations
 of runoff could make it necessary to install additional sediment barriers, sediment traps, etc.)
 Assessing the need for additional controls and implementing them or adjusting existing controls will
 be a continuing aspect of this SWPPP until the site achieves final stabilization.

Stormwater Pollution Prevention Plan