TOWN OF ORCHARD PARK
  ENGINEERING  DEPARTMENT
  S 4295 South Buffalo Street  Orchard  Park, New York 14127-2609

  Phone:  (716) 662-6425  TOWN ENGINEER
  Email:  [email protected]  WAYNE  L. BIELER,  PE., CFM

 April 30, 2026

Honorable Town Board
Town of Orchard Park
4295 South Buffalo Street
Orchard Park, New York 14127

Re:  Berg Road Pump Station Replacement Project - General
  Final Change Order & Release of Retention
Dear Board Members:

| am pleased to inform you that construction work the Berg Road Pump Station Replacement
Project — General has been completed. On September 25, 2025, a final inspection was
conducted, and all of the work has since been satisfactorily completed in accordance with the
contract documents and specifications.

A two-year maintenance bond, in the amount of $609,408.54, has been submitted along with
the Affidavit of Release of Liens, Affidavit of Subcontractor Payment, and necessary legal
documents.

Attached is a copy of the final project Change Order and associated Over/Under sheet. The
Over/Under sheet lists the final adjustments to the quantities for each bid item and shows
there will be a net decrease  of $2,376.92.  This represents  a decrease of 0.39% from the
original amount bid with change orders.
|, therefore, recommend that you adopt the following resolutions:

  e  Approve the release of retention and final payment for the Berg Road Pump Station
  Replacement Project — General to Ground Breaking Solutions, 1019 Blakeley Road,
  East Aurora, NY 14052, in the amount of $33,118.92.
  e  Authorize the Town Clerk to release Ground Breaking Solutions’ performance security
  for the Berg Road Pump Station Replacement Project — General in the amount of
  $598,000.00.
Respéctfully submitted,

Wayne. Bieler, P.E., CFM
Town Engineer
Attachment
Cc:  William Evan, Town Clerk  Timothy Gallagher, Town Attorney
  Andy Slotman, OP Highway Superintendent  File #2020.005
S:\Town Projects\Berg Rd Pump station 2020.005\Construction\Letter to TB CLOSEOUT LETTER Berg Road Pump Station