FINAL CHANGE ORDER - OVER / UNDER SHEET
 PROJECT:  Berg Road  Pump  Station  Replacement - Generql
 PROJECT NO. : :2002.005
 DATE:  4/30/2026
 BY:  TAO
  ITEM NO.  DESCRIPTION  UNIT  ROUND  UNIT BID  TOTAL  FINAL  OVER  ADD  UNDER  DEDUCT
  QUANTITY  PRICE  QUANTITY
 1  Mobilization/Demobilization  Ls  $17,000.00  1  17,000.00  100%
 2  Insurances and bonds  LS  21,300.00)  1  21,300.00  100%
 3  Bypass pumping  L$  19,700.00)  1  19,700.00  100%
 4  Tree removal  LS  $23,000.00  1  23,000.00  100%
 5  [Driveway Prep  LS  530,000.00  1  30,000.00  100%
 6  Asphalt driveway paving  LS  $33,000.00  1  $33,000.00  100%
 7  Shallow Manhole  LS  $29,000.00  1  29,000.00  100%
18  Valve Vault  LS  $30,000.00  1  30,000.00  100%
 9  Valve Vault Piping  LS  $21,000.00  1  21,000.00  100%
 10  Pump  Station  LS  $58,000.00  1  $58,000.00  100%
 11  Pump  Station Piping  LS  $30,000.00  1  $30,000.00  100%
 12  Pump Station Pumps  LS  $60,000.00  1  $60,000.00  100%
 13  Forcemain piping  LS  $15,000.00  1  15,000.00  100%
 14  Deep dog house manhole  LS  $38,000.00)  1  $38,000.00  100%
 15  [Stormwater Piping  LS  $8,000.00)  1  $8,000.00  100%
 16  Precast concrete floor for building  Ls  $33,200.00)  1  $33,200.00  100%
 17  Ls  $90,000.00  1  90,000.00  100%
 18  Building  MEP  LS  $10,000.00)  1  10,000.00  100%
  Erosion and sediment control  LS  $10,000.00  1  10,000.00  100%
 20  Bi  rds  LS  $6,000.00  1  $6,000.00  100%
 21  [potars and seed restoration  Ls  $11,000.00  1  $11,000.00  100%
 22  Naturai Gas Allowance  Ls  $2,623.08  1  $2,623.08  52%  $2,376.92  $2,376.92
 23  CO# 1A Doghouse and shallow Manhole Modification  Ls  7,397.57  1  $7,397.57  100%
 24  CO# 1B Asbestos Abatement  Ls  3,600.00  1  $3,600.00  100%
 25  CO# 2 Float Relocation  LS  3787.89  1  53,787.89  100%
  ADD:  $0.00  DEDUCT:  ($2,376.92)
  ADD:  $0.00
  DEDUCT:  ($2,376.92)
  NET CHANGE:  ($2,376.92)
  ORIGINAL CONTRACT AMOUNT:  $598,000.00
  PREVIOUSLY  APPROVED  CHANGE  ORDERS:  $13,785.46
  SUBTOTAL:  $611,785.46
  FINAL CHANGE ORDER:  ($2,376.92)
  FINAL CONTRACT AMOUNT: