Appendix B
APPENDIX B – Required SWPPP Components by Project Type
  Table 1
  CONSTRUCTION ACTIVITIES THAT REQUIRE THE PREPARATION OF A SWPPP
  THAT ONLY INCLUDES EROSION AND SEDIMENT CONTROLS

 The following construction activities that involve soil disturbances of one (1) or more acres of
 land, but less than five (5) acres:

  • Single-family home not located in one of the watersheds listed in Appendix C and not directly
  discharging to one of the 303(d) segments listed in Appendix D
  • Single-family residential subdivisions with 25% or less impervious cover at total site build-out and
  not located in one of the watersheds listed in Appendix C and not directly discharging to one of the
  303(d) segments listed in Appendix D
  • Construction of a barn or other agricultural building, silo, stock yard or pen.
  • Structural agricultural conservation practices as identified in Table II in the “Agricultural Best
  Management Practice Systems Catalogue” (dated June 2023) that include construction or
  reconstruction of impervious area or alter hydrology from pre- to post-development conditions.

 The following construction activities that involve soil disturbances between five thousand (5000)
 square feet and one (1) acre of land:

  • All construction activities located in the New York City Watershed located east of the Hudson River,
  see Appendix C Figure 1, that involve soil disturbances between five thousand (5,000) square feet
  and one (1) acre of land.

 Within the municipal boundaries of NYC:

  • Stand-alone road reconstruction, where the total soil disturbance from only that road construction, is
  less than one (1) acre of land.

 The following construction activities:

  • Installation of underground linear utilities; such as gas lines, fiber-optic cable, cable TV,
  electric, telephone, sewer mains, and water mains
  • Environmental enhancement projects, such as wetland mitigation, stormwater retrofits, stream
  restoration, and resiliency projects that reconstruct shoreline areas to address sea level rise
  • Pond construction
  • Linear bike paths running through areas with vegetative cover, including bike paths surfaced with an
  impervious cover
  • Cross-country ski trails, walking/hiking trails, and mountain biking trails, including a de minimis
  parking lot (maximum 10 spaces total, sized for passenger cars) with 35 feet minimum preservation
  of undisturbed area downgradient from the parking lot
  • Dam rehabilitation (the structure of the dam itself)
  • Sidewalks, bike paths, or walking paths, surfaced with an impervious cover, that are not part of
  residential, commercial, or institutional development;
  • Sidewalks, bike paths, or walking paths, surfaced with an impervious cover, that include incidental
  shoulder or curb work along an existing highway to support construction of the sidewalk, bike path,
  or walking path.

  64

  Page 770 of 849