ob *|

  TOWN OF ORCHARD PARK
  ENGINEERING  DEPARTMENT
  S 4295 South Buffalo Street  Orchard Park, New York 14127-2609

  Phone:  (716) 662-6425  TOWN ENGINEER
  Email:  [email protected]  WAYNE  L.  BIELER,PE.,  CFM

August 12, 2026

Honorable Town Board
Town of Orchard Park
4295 South Buffalo Street
Orchard Park, New York 14127

Re:  Community Activity Center — Generator Installation Project
  Final Change Order & Release of Retention (Electrical Contact)

Dear Board Members:

I am pleased to inform you that construction work for the electrical construction contract, on the
Community Activity Center Generator Installation Project, has been completed. On April 28, 2026, a final
inspection was conducted, and all Final Punch List work has since been satisfactorily completed in
accordance with the contract documents and specifications.

A two-year maintenance bond, in the amount of $130,532.00, has been submitted along with the Affidavit
of Release of Liens, Affidavit of Subcontractor Payment, and necessary legal documents.

I, therefore, recommend that you adopt the following resolutions:
e  Approve the final change order and authorize release of the retention for the Community Activity
  Center Generator Installation Project, (Electrical Contract) to Stenzel Electrical Construction Inc.,
  8535 Sunset Drive, Williamsville, New York 14221, in the amount of $10,326.60 (attached).
e  Authorize the Town Clerk to release Stenzel Electrical Construction Inc. performance security in the
  amount of  $119,250.00.

Respectfully submitted,

Wayne L Bieler, P.E., CFM
Town Engineer  _

Attachments: Final Change Order & Release of Retention

Ce:  William Even, Town Clerk
  Timothy Gallagher, Town Attorney
  Nichole Ruf, Dresser & Malecki
  Dave Stenzel, Stenzel Electrical Construction Inc.

  File: 22/23 CARES ACT
S:\Town Projects\Town Facilities\CAC Grant - Generators & Openers\Generators\EC Construction\TB-FINAL PAYMENT LETTER-
CAC Generator Project_EC.dqe
  I sit the Town’s website at www.orchardparkny.gov