Proposed EV Charging Stations  Site Plan Review
705 Orchard Park Road  Page 2 of 2
West Seneca, NY 14224

Stormwater
The project will disturb ±0.14 acres of land and substantially decrease green space. To mitigate
stormwater runoff, an underground pipe detention system is proposed to reduce post construction
discharge rates to pre-existing discharge rate. The intent would be to utilize perforated pipe to allow for
infiltration. Infiltration testing will be completed to confirm the design.

Construction Schedule
The intent would be to start construction once all municipal approvals and permits are obtained. It is
estimated that the duration of construction will be ±4 weeks.

We look forward to presenting this information at the May 14th Town Planning Board meeting. If you have
any questions, please do not hesitate to contact our office.

Sincerely,
BOHLER ENGINEERING NY, PLLC

Randy Bebout

Cc:
James Rambone, New Leaf Energy

  www.BohlerEngineering.com

  Page 20 of 1493