PART 8 General Development Standards  97 OF 148

J.  Certification. The applicant shall provide the  K. Monitoring requirements for wind energy
  following certifications:  conversion systems.

  1.  Certification of structural components.  1.  Right to enter premises for monitoring. Upon
  The foundation, tower and compatibility of  reasonable notice, City of Lackawanna
  the tower with the rotor and rotor-related  officials or their designated representatives
  equipment shall be certified in writing by a  may enter a lot on which a WECS facility
  structural engineer licensed and registered  permit has been granted for the purpose of
  in New York. The engineer shall certify  compliance with any permit requirements.
  compliance with good engineering practices  Twenty-four hours' advance notice by
  and compliance with the appropriate  telephone to the owner/operator or
  provisions of the Uniform Building and  designated contact person shall be deemed
  Construction Code that have been adopted  reasonable notice.
  in New York State.  2.  Avian/bat impact study plan. The applicant
  2.  Certification of post construction. After  shall submit a plan for monitoring the avian
  completion of the wind energy conversion  impact of the commercial wind energy
  system, the applicant shall provide a  facility to the Planning Board for its review
  postconstruction certification from a  and approval. Such plan shall document
  licensed professional engineer licensed and  and follow accepted scientific study
  registered in the State of New York that the  procedures. In addition, the applicant shall
  project complies with applicable codes and  agree to submit a report to the Planning
  industry practices and has been completed  Board according to the requirements of the
  according to the design plans.  applicable regulatory agencies that identifies
  3.  Certification of electrical system. The  all dead birds found within 500 feet of the
  electrical system shall be certified in writing  commercial wind energy facility.
  by an electrical engineer registered in New  3.  Periodic reporting required. The applicant
  York. The engineer shall certify compliance  shall agree to submit periodic monitoring
  with good engineering practices and with the  reports to the City. The report shall contain
  appropriate provisions of the Electric Code  data on the operations and environmental
  that have been adopted by New York State.  impacts and shall be in the form prescribed
  4.  Certification of rotor overspeed control. The  by the Code Enforcement Officer.
  rotor overspeed control system shall be  4.  Power production report required. The
  certified in writing by a mechanical engineer  applicant shall agree to submit as requested
  licensed and registered in New York State.  by the City Council a power production
  The engineer shall certify compliance with  report to the City. The power production
  good engineering practices.  report shall include actual power production
  5.  Certification of project. A certificate of  in kilowatt hours for each WECS facility.
  completion must be supplied by the
  applicant and approved by the City of
  Lackawanna Code Enforcement Officer.