PART 8 General Development Standards  99 OF 148

  5.  Not detrimental to the public health, safety  S. The applicant shall certify to the City that
  and general welfare of the community.  appropriate security will be in place to restrict
  The proposed WECS facility will not he  access to the WECS and facilities following
  detrimental to the public health, safety or  completion of construction.
  general welfare of the community.
  6.  Complies with all required provisions
  §8-17-6 Wind measurement towers
  of the Zoning Ordinance. The proposed  [Amended 3-5-2008]
  WECS facility shall comply with all required
  provisions of the Zoning Ordinance, unless  The City Council acknowledges that prior to
  variances have been properly applied for and  construction of a WECS, a wind site assessment
  granted pursuant to Part 11 of this Chapter.  is conducted to determine the wind speeds and
  feasibility of using particular sites. Installation of wind
N. The City Council may grant the special use
  measurement towers, also known as "anemometer
  permit, deny the special use permit, or grant the
  ("met") towers," shall be permitted as a special use in
  special use permit with written stated conditions.
  the same zoning districts as the WECS.
  Denial of the special use permit shall be by
  written decision based upon substantial evidence  A. An application for a wind measurement tower
  submitted to the Board. Upon issuance of the  shall include:
  special use permit, the applicant shall obtain a
  1.  Name, address and telephone number of the
  building permit for each tower.
  applicant. If the applicant is represented by
O. WECS permits approved by the City Council  an agent, the application shall include the
  of the City of Lackawanna shall be renewed  name, address and telephone number of the
  annually. The permit holder shall make renewal  agent as well as an original signature of the
  application to the Supervising Building Inspector  applicant authorizing the representation.
  60 days prior to expiration to allow for inspection
  2.  Name, address and telephone number of the
  and full compliance with all applicable laws and
  property owner. If the property owner is not
  regulations. The renewal application will include
  the applicant, the application shall include
  a fee as set by the City Council of no more than
  a letter or other written permission signed
  $500 per wind energy system.
  by the property owner confirming that the
P.  The special use permit shall not be assignable  property owner is familiar with the proposed
  or transferable without the approval of the City  applications and authorizing the submission
  Council.  of the application.
Q. Amendments to special use permit. Any changes  3.  Address of each proposed tower site,
  or alterations postconstruction to the WECS shall  including Tax Map section, block and lot
  be done only by amendment to the special use  number.
  permit and subject to all requirements of this
  4.  Site plan.
  article.
  5.  Decommissioning plan, including a security
R. The applicant licensee shall agree to indemnify
  bond or cash for removal.
  and hold the City, its City Council, officers, agents
  and employees harmless from any liability  B. The City Council may attach such conditions as
  imposed upon the City, its officers, agents and/  it deems appropriate to variance approvals as it
  or employees arising from the construction,  deems necessary to minimize the impact of the
  operation or maintenance of the WECS.  variance.
  C. The "Met" towers installed prior to February 1,
  2008 shall be exempt from the requirements set
  forth in this section.