100 OF 148  CITY OF LACKAWANNA • NY 2026 ZONING ORDINANCE | Chapter 300: Zoning

  §8-17-7  Permit Revocation  §8-17-8 Fees and costs
  A. Testing fund. A special use permit shall contain  [Amended 3-5-2008]
  a requirement that the application fund periodic
  A. All fees required under this article shall be
  noise testing by a qualified independent third-
  approved by the City Council by resolution.
  party acoustical measurement consultant, which
  Nothing in this article shall he read as limiting the
  may be required as often as every two years or
  ability of the City to enter into host community
  more frequently upon request of the City Council
  agreements with any applicant to compensate
  in response to complaints by residents. The
  the City for expenses or impacts on the
  scope of the noise testing shall be to demonstrate
  community. The City shall require any applicant
  compliance with the terms and conditions of the
  to enter into an escrow agreement to pay the
  special use permit and this article and shall also
  engineering and legal costs of any application
  include an evaluation of any complaints received
  review, including the review required by SEQRA.
  by the City. The applicant shall have 90 days after
  written notice from the City Council to cure any
  §8-17-9  Enforcement; Penalties for
  deficiency. An extension of the ninety-day period
  may be considered by the City Council, but the
  Offenses; Remedies
  total period may not exceed 180 days.  A. Any person owning, controlling or managing any
  B. Operation. A WECS shall be maintained in  building, structure or land who shall undertake
  operational condition at all times, subject to  a WECS or wind measurement tower in violation
  reasonable maintenance and repair outages.  of this article or in noncompliance with the terms
  Operational condition includes meeting all noise  and conditions of any permit issued pursuant to
  requirements and other permit conditions. Should  this article or any order of the enforcement officer
  a WECS become inoperable, or should any part of  and any person who shall assist in so doing shall
  the WECS be damaged, or should a WECS violate  be guilty of an offense and subjected to a fine
  permit conditions, the owner or operator shall  of not more than $250 or to imprisonment for a
  remedy the situation within 90 days after written  period of not more than six months, or both. Every
  notice from the City Council. The applicant shall  such person shall be deemed guilty of a separate
  have 90 days after written notice from the City  offense for each week such violation shall
  Council to cure any deficiency. An extension of  continue. The City may institute a civil proceeding
  the ninety-day period may be considered by the  to collect civil penalties in the amount of $250
  City Council, but the total period may not exceed  for each violation, and each week said violation
  180 days.  continues shall be deemed a separate violation.

  C. Notwithstanding any other abatement provision  B. In case of any violation or threatened violation
  under this article, if the WECS is not repaired  of any of the provisions of this article, including
  or made operational or brought into permit  the terms and conditions imposed by any permit
  compliance after said notice, the City may, after  issued pursuant to this article, in addition to
  a public hearing at which the operator or owner  other remedies and penalties herein provided,
  shall be given opportunity to be heard and  the City may institute any appropriate action or
  present evidence, including a plan to come into  proceeding to prevent such unlawful erection,
  compliance, either order remedial action within  structural alteration, reconstruction, moving and/
  a particular timeframe or order revocation of the  or use, and to restrain, correct or abate such
  wind energy permit or the WECS and require the  violation to prevent the illegal act.
  removal of the WECS within 90 days. If the WECS
  is not removed, the City Council shall have the
  right to use the security posted as part of the
  decommission plan to remove the WECS.