come back with a higher water table than expected, an impermeable liner will be installed in stormwater practices within that area(s). Attached with this submission are the following revised items: • C301 – Utility Plan • C302 - Utility Plan • C401 – Grading Plan • Compiled SWPPP – Revised July 2026 • Pipe Sizing Calculations – Revised July 2026 We look forward to presenting this project to the Planning Board on August 13th, 2026. If you have any questions or need any additional information, please feel free to contact me at 585-770-2525 or [email protected]. Respectfully submitted, LaBella Associates Shelby Vakiener Civil Engineer 3 Page 337 of 1174