103  OPERATOR’S NAME AND ADDRESS

  Benchmark Streamline, LLC

  4053 Maple Road

  Amherst, NY 14226

  Contact Person: Jared Lemankiewicz

  Telephone: 716-876-0160

104  PROJECT DESCRIPTION

  This project consists of the first phase of the redevelopment of the approximately 56 acre former Seneca
  Mall property, located within the area bounded by Slade Avenue, Ridge Road, and Orchard Park Road in
  the Town of West Seneca. The proposed redevelopment includes construction of an approximately
  158,000 square foot commercial building to be occupied by Costco Wholesale, along with associated
  parking, utilities, stormwater management facilities, and other supporting site improvements. This phase
  also includes the primary infrastructure necessary to accommodate future phases and the ultimate full
  build out of the redevelopment site.

  Proposed site improvements include upgrades to the existing utility infrastructure, construction of a new
  internal roadway network, parking facilities, site lighting, landscaping, and stormwater management
  system designed for the full build out. These improvements are intended to provide the framework
  required for future development throughout the remainder of the property.

  The project site is currently occupied by the remnants of the former Seneca Mall and the existing Tops
  Market grocery store. The Tops Market will remain operational throughout construction and will not be
  impacted by the proposed redevelopment. Construction activities associated with the redevelopment are
  expected to result in approximately 27.71 acres of land disturbance.

Soil disturbing activities will include:

  A.  Construction of temporary construction exit points

  B.  Clearing & grubbing of the site within disturbance limits

  C.  Installation of the detention basin & bioretention areas including topsoil & seed

  D.  Installation of storm sewer pipes and inlets

  E.  Construction of utilities

  F.  Construction of curb and parking lot

  G.  Final grading & landscaping

  H.  Construction of buildings

  This project is owned by Benchmark Streamline, LLC and will be developed by the same. The work area
  consists of approximately 27.71 acres for which erosion and sediment controls have been developed and
  fully addressed in this written plan and the Erosion and Sediment Control Plans. See the construction
  documents for additional details.

West Seneca Exchange
07/20/2026