National Grid Site Plan and Public Utility Use Variance Application August 14, 2026 Page 5 infrastructure and replacement equipment. The marshalling yard was first constructed upon approval by the PSC, who regulates all electric service providers in the State. Under the Public Service Law, the PSC approved the Property to serve as a marshalling yard to support National Grid’s GD 141/142 project. See Exhibit 7. Prior approval by the PSC in the Article VII process indicates this location is strategic and beneficial to the logistics of completing National Grid’s essential mission. Having a permanent marshalling yard in the Town allows National Grid to adequately service many Western New York lines and upgrade aging infrastructure. The Property is ideally situated for just that due to its proximity to over 33 pending National Grid improvement projects. See Exhibit 5. Given the location adjacent to the thruway on and off ramps, National can use the marshalling yard for more than just the infrastructure and projects identified within the 15-mile radius. Improved infrastructure supports orderly development, health and safety, while also facilitating the adequate provision of essential electricity services in the Town and larger region. b. There are no existing viable alternatives. The Property is located next to National Grid’s 3-phase distribution circuit. This allows National Grid to quickly respond to any outages or repairs on this line. The Property is also located near many other western NY lines and substations. As discussed above, proximity to 33 pending projects means National Grid can stage and improve electrical infrastructure across its western New York footprint. Further, the Property is already cleared/disturbed with sufficient open land. The Property was strategically selected given the Property’s topography, existing vegetation, suitable open land and proximity to National Grid infrastructure. Finally, the Property has historically been used as a marshalling yard and is situated in a low-development area. c. Community intrusion is minimal. “[W]here the intrusion or burden on the community is minimal, the showing required by the [applicant] should be correspondingly reduced.” Consolidated Edison Co. of New York v Hoffman, 43 NY2d 598, 611 (1978). The Property minimizes potential environmental impacts as there is no contamination history at the project site, no unique geological features, it is not located in a floodplain, and it will have no impact on any archaeological or historic sites. Applicant’s minimal proposed land disturbance on site includes the installation of vegetative screening. Grading (except for the filling of a few potholes and ruts) and below grade disturbance is not anticipated. While the existing yard is an impervious gravel area with permanent fencing and gates, Applicant does expect that a few perimeter controls may be needed as part of the site upgrades. Importantly, the marshalling yard complies with all underlying setback requirements.