Text · page 125 of 241
Read the whole document on one page (all 241 pages, each with its own heading)
Yes – this 1 small Boston State Road Between Meadow & Ripple section took 3 years Watermain Replaced in 2022/2023 from start to finish! Received $150,000 CDBG grant / ARPA Funds Covered the Remainder Total Project Cost: $491,881 January 2021 March 2022 Awarded Resolution 2022- September 2023 $150,000 13 Award Final Asphalt top CDBG Construction Bid course February 2021 August 2022 2024 Resolution Resolution 2022-58 Close out Final bill 2021-13 Contract, Enter Short-Form paid to New Engineering Agreement for Come Back Work Frontier 125