Water Line Replacements – Phase 1 (Sept 2022 updated costs) 1 year later, the 2021 estimate of $3.8 million for Phase 1 is now $5.2 million In one year, cost estimate rose from $3,836,370 to $5,188,005 (up $1,351,635) At this point (2022): • In Engineering design stage • Hoping to get DOH/ECWA approvals late 2022/early 2023 (Did not actually come through till Summer 2024) • Hoping to go out to bid in February/March 2023 (Actually ended up being July/August 2024) • Construction summer of 2023 (Actually awarded end of 2024/ construction in 2025-2026) Financing: • WIIA – 2021 & 2022 applications on full project denied. Applied in 2023 -2026 for just phase 2 & 3. • BAN (Bond Anticipation Note) – will go out to financing after bids received. Bond Resolution from November 2021 initiated this and was amended in July 2023 for updated costs (BAN issued October 2024) 140