Water Line Replacements – Phase 1 Status Update (October 2025) 2 Change Orders were approved, (both per discussions with ECWA and NYSDOT) 1st was regarding moving the Heinrich Section into the road 2nd relates to changes in the planned Creek & Road Crossings Project still running lower than initial cost estimates ($2,774,000 from 2021 or $3,851,000 from 2023)… Additional costs will be paid for from interest earned on the BAN or pulled out of Fund Balance 155