Water Line Replacements – Financing for Phase 2 (Oct 2026) Phase 2 Engineering Costs $ 991,130 Geotechnical Study $ 77,900 Wetlands Delineation $ 11,703 At the October 2026 BAN Archaeology Study $ 4,795 Renewal for the Water Rounding to nearest thousand $ (528) Tanks, the Town also NEW Amount Financed by BAN $ 1,085,000 issued new money for Phase 2 Engineering & Phase 1 Amount Re-Issued $ 2,675,000 Preparatory Studies Water Tank Amount Re-Issued $ 915,000 Total 2026 BAN Issued $ 4,675,000 171