Town Hall Generator June to August September August 2024 2023 2024 September Prep work at 2024 Awarded bid to Approve Change Town Hall… pour Industrial Power Order on Generator set in concrete pad, & Lighting Corp. Electrical place hook up gas & (IPL) Hookups prep electric Resolution 2023-27 Approve Engineering Quote: $20,000 Resolution 2023-76 Approve Construction Bid: $222,400 October 2025 Final closeout Resolution 2024-54 Approve Change Order: $34,365 Construction Cost - Per Bid $ 222,400 CCN02 – Abandon the existing electrical feeders and run entirely new from the pole as shown. The electrical feeders Construction Cost - Change Order $ 34,365 would be directionally drilled underneath the existing driveway into the new manhole. Cost is $34,364.93 Engineering Cost $ 20,000 Total Revised Project Cost: $ 276,765 199