Town Hall Entryway Needed full replacement of stairs, handrails, and pillars Bid Opening • 6 bids received • Low Bid - Double A Services $46,525 • 2nd Lowest – Kirst Construction $52,200 Front Steps Concrete (April 2024) • Tear out went quickly • 1st pour – concrete was wavy • 2nd pour – ponding water • 3rd pour – Good! Column Replacement (thru June 2025) Engineering Cost • Columns removed / temporary supports installed • Bases poured • October 2024 – Still awaiting new columns • February 2025 – Terminated Contract with Double A…. Approved Kirst to come finish the work for $15,500 • June 2025 – Completion, Payment, & Project Close-out 201