Utilities - Electricity LANCASTER, N.Y. — June 16, 2026 — New York State Electric & Gas (NYSEG) has completed its upgrades to the Cobble Hill Substation, which will improve reliability, resilience, and capacity for customers in the towns of Boston, Colden, East Concord, and Glenwood. This substation serves approximately 3,700 customers in Western New York. The investment is part of Avangrid and NYSEG’s investment plan to improve grid infrastructure through 2030 to meet the growing energy demands on homes and businesses and protect the community against severe weather events. The substation is located on Hunn Road and is approximately 50 years old. This spring, NYSEG procured a 56 MVA transformer which will provide the energy load for the community. 98