Southtowns Record

TBA01.26.2026packet

Government
Town of West Seneca
Board
Town Board
Meeting
Jan 26, 2026, 6:00 p.m.
Posted by publisher
Jan 23, 2026
Kind
Agenda packet
Topics
Water, sewer and drainage, Budget and taxes, Public safety, Parks and recreation, Zoning and land use, Roads and traffic, Audits and oversight, Housing

Original document

Same meeting

Text · page 156 of 301

Read the whole document on one page (all 301 pages, each with its own heading)

David Woolley | QA/QC - Water

30-Inch Raw Watermain Replacement Project  Hamburg Victory Avenue Waterline
Engineer |
  Replacement
City of Lockport | Lockport, NY | 2018  Engineer |
Assisted in the detailed design for the replacement of  Village of Hamburg | Hamburg, NY | 2015
approximately 12,000 feet of 30-Inch raw watermain.  Dave completed the detailed design and preparation of
The raw watermain is City’s only source of water and the  contract documents for the replacement of a waterline in
project was declared an Emergency Situation; therefore,  Hamburg, NY. Assisted in design of the waterline and
in depth consideration was given to maintaining water  was responsible for acquiring all necessary agency
supply to the City through construction sequencing.  approvals.
Dave assisted with pipeline alignment, materials of
construction, and assembly of all contract documents.  South New York Street Waterline Replacement
Responsible for coordinating all permitting efforts with
various entities. Dave was also the lead Contract  Engineer |
Administrator throughout the construction phase of the  City of Lockport | Lockport, NY | 2015
project and coordinated between involved parties and  Responsible for the design and assembly of technical
tracked budgets.  specifications for the upgrade and replacement of a
  waterline in Lockport, NY. Coordinated with City officials
Water Tank Painting Project  and other agencies to acquire necessary approvals.
Engineer |
Town of Pendleton | Pendleton, NY | 2017  Parsons Development Area Water Transmission
  Main Phase 2 Valve Chamber Repairs
Dave completed the detailed design and preparation of
contract documents for the exterior painting and  Engineer |
rehabilitation of a water storage facility in Pendleton, NY.  Regional Municipality of Wood Buffalo | Fort
Design Engineer for the necessary rehabilitation and  McMurray, AB | 2015
painting, and was responsible for acquiring all necessary  Dave aided in the design and permitting for repairs to a
agency approvals  valve chamber on a water transmission main. He was
  responsible for assembling technical specifications and
Water Tank Interior Painting Project  assisted in submittal reviews.
Engineer |
Town of Pendleton | Pendleton, NY | 2016  Career history
Completed the detailed design and preparation of  2015 – present  GHD, Civil Engineer/Civil
contract documents for the interior painting and  Engineering Design Manager -
rehabilitation of a water storage facility in Pendleton, NY.  Northeast
Assisted in design of the necessary rehabilitation and
painting and was responsible for acquiring all necessary  2014 - 2015  PCS Crane & Rigging Company,
agency approvals.  Intern
  2013 - 2014  Clark Patterson Lee Design
Water System Improvements  Professionals, Intern
Engineer |
Town of Eden | Eden, NY | 2016
Dave was responsible for the preparation and assembly
of the U.S. Army Corps of Engineers Joint Application
for Permits. The permit covered various watermain
crossings under Eighteen Mile and Ryther Creeks.

T +1 716 362-8802 | E [email protected]  www.ghd.com