Southtowns Record

TBA01.26.2026packet

Government
Town of West Seneca
Board
Town Board
Meeting
Jan 26, 2026, 6:00 p.m.
Posted by publisher
Jan 23, 2026
Kind
Agenda packet
Topics
Water, sewer and drainage, Budget and taxes, Public safety, Parks and recreation, Zoning and land use, Roads and traffic, Audits and oversight, Housing

Original document

Same meeting

Text · page 93 of 301

Read the whole document on one page (all 301 pages, each with its own heading)

EXPERIENCE

Village of Arcade
Sanitary Sewer Inflow & Infiltration Studies
GRANT FUNDED

Location: Arcade, NY  report included mapping showing locations of
Client: Village of Arcade  manholes, spot repairs/replacement and other sewer
Completion Date: Phase 1-2017,  deficiencies. It also offered a detailed cost estimate of
Phase 2A-2019, Phase 2B-2020  the recommended improvements which consisted
  of the open cut replacement of sanitary sewer main,
  rehabilitation of manholes and the replacement of
Inflow and Infiltration (I&I) is an ever-present problem
  manholes.
in the Village of Arcade sanitary sewer system. In 2013,
CPL completed a study of the entire sanitary sewer
  The evaluation for Phase 2A and Phase 2B for the
collection system by performing flow monitoring in
  Southeast Service Area and North Service Area,
order to identify the problematic areas of the Village’s
  consisted of approximately 9,000 feet of 8-inch
five sanitary sewer collection service areas. As a
  sanitary sewers and approximately 48 manholes. For
result of the study, the service areas were ranked
  both Phases, CPL coordinated the televising work,
and prioritized based on their deficiencies for further
  completed a visual inspection of the existing sanitary
investigations and future rehabilitation.
  manholes within the service area, coordinated smoke
  testing and tabulated findings; reviewed and evaluated
For Phase 1, CPL performed additional inflow and
  televising and manhole inspection data. Engineering
infiltration (I&I) evaluation of the Village’s northeast
  Reports were prepared for both Phases with the
service area by completing televising of the sanitary
  findings and offered recommendations and priorities
mains, inspection of manholes and smoke testing.
  for improvements to be made along with detailed cost
The area consisted of approximately 12,885 feet of
  estimates of the recommended improvements. The
8-inch and 12-inch sanitary sewers and approximately
  improvements consisted of the open cut replacement
58 manholes. An Engineering Report was prepared
  of sanitary sewer main, rehabilitation of manholes and
with the findings and offered recommendations
  the replacement of manholes.
and priorities for improvements to be made. The