ECSD No. 3 Boatd of Managers
  February I l, 2026 Meering lvlinures
  Page 4 of 6

All process and electrical systems have been operating as expected with minor items from
completed construction still being addressed through the punch list.

Contract No. 75 (Southtowns AWTF Expansion Phase 2) - This project is expected to bid in
2026, pending NYSDEC approvals and a new SPDES permit.

Contract 80 - Central Region Collections Facility - Masonry work has been finished.
Locker room and offrce construction are being complete, including installation of intemal
electrical items. Due to delays involving the NYSEG electrical utility service, completion of
this project will be delayed into Spring 2026. A meeting will be held with NYSEG to
address these issues.

  I  uthtowns AWTF  U  - This
project is in the shop drawing submittal and approval stage which will be followed by ari
anticipated lengthy equipment procurement timeframe. Onsite work for this project could
start as late as 2027 . T\e scheduled Contract completion date is July 19, 2028.

Contract No. 82 (Southtowns AWTF Landfill Reclamation) - All work for this project has
been completed and the Contract is being closed out ahead ofthe completion date of March
4,2026. Closeout was requested earlier in this meeting.

Contract 84 -  Force Main Air Release V ve Replacement - STC Construction
commenced work on this project in November 2025. A new doghouse manhole was installed
on Jamison Road east of Bowen Road. Due to manufacturer delays, the work to replace the
two (2) deteriorated air release valves is anticipated to be delayed until Spring 2026. A no-
cost time extension was approved, extending the project completion date from December 14,
2026 to May 22,2026.

Contract 95 (C IPPL Term Contract) (USI  von Pioeline) - United Survey continued
cured-in-place pipe lining (CIPPL) work under Work Order (WO) 8U which includes 11,420
linear feet of S-inch, l0-inch and 12-inch diameter Vitrified Clay Tile Pipe (VTP) and
Asbestos Cement Pipe (ACP) sewerlines on various streets in the Town of Hamburg
(including Amsdell Road, Orchard Ave., Lyndale Ave., Hawthome Ave., Greenfield Ave.,
Femdale Ave., Southcrest Ave,, Oakwood Ave., Lakewood Ave., Riverton Ave., Woodlawn
Ave., and Glendale Ave.). Kenyon Pipeline continued lining work under WO l5K which
includes 13,394 linear feet of 8-inch diameter VTP sewers on Amsdell Road and Crestridge
in the Town of Hamburg; various VTP sewerlines in the Village of Hamburg (Evans St.,
Central Ave., Long Ave., S Buffalo St., Center St., Woodview Ave., Highland Ave.). The
work order also includes one pipe patch on an easement along Abbott Road near the
Hamburg/Orchard Park boundary

Contract 96  ultiDistrict) - Sanitarv  Ooen Cut Reoair Term C ontract - (Visone
Construction) - In the spring, restoration activities will be completed for a sewer replacement
 ocated on Pleasant Ave. at church St. in the village of Hamburg. Remaining work includes
sidewalk replacement, lawn restoration, and tree replacement.