  Load (MVA)  10

  8

  6  7.30
  6.1
  4

  2
  46.89%  56.10%
  0
  2025 Peak  Diversified Load
  (Pre-construction)  (Post Construction)

  Chart 1. Peak Load Capacity

Based on the post development conditions, we believe that the new development may be able to be
serviced without any upgrades needed to the existing circuit. The most cost-effective solution would
be to utilize the existing service, however new transformers and conductors may be required due to
the additional load.

5.0  OPINION OF PROBABLE CONSTRUCTION COST

A conceptual construction cost estimate for this project was not developed at this time since the post
construction loading is well below the assumed limit for upgrades. Please note that there will be a
cost payable to NYSEG/RGE for the installation of service equipment.

6.0  CONCLUSION

Based on this evaluation, the proposed project will increase the load on the existing 12.5kV circuit to
56.1% of its capacity. This is below the anticipated maximum peak percentage; therefore, it is our
opinion that project can be serviced without additional upgrades from the utility.

  -3-
  Utility Grid Capacity Evaluation
  GCE West Seneca
  LaBella Project No. 2243432

  Page 32 of 110