Village of East Aurora Water System Improvements  July 2026
SEQRA Part 3 Supporting Information

  8.  Impacts on Agricultural Resources

  The proposed project does not intersect an Agricultural District or areas
  identified as important agricultural land. The project consists of improvements
  to the existing municipal water distribution system within developed roadways,
  roadway rights-of-way, and existing utility facilities. No conversion of
  agricultural land, disruption of agricultural operations, or impacts to agricultural
  resources are anticipated.
  9.  Impacts on Aesthetic Resources

  9.a.  Proposed action may be visible from any officially designated federal, state, or
  local scenic or aesthetic resource.

  Temporary construction activities associated with water main installation will be
  visible from public roadways, nearby parks, and surrounding developed areas
  throughout the project corridor. These temporary visual effects will be limited
  to the construction period and will not result in permanent changes to the visual
  character of the project area. The proposed rehabilitation of the existing water
  storage tanks will consist primarily of exterior cleaning and repainting and will
  not substantially alter their existing appearance. The replacement
  hydropneumatic pump system will be constructed within the footprint of the
  existing booster pump station and is not expected to result in noticeable
  changes to visual conditions. Any tree clearing required for construction will be
  limited to the minimum extent practicable. Overall, the proposed action will
  maintain the existing visual character of the project area following completion
  of construction.

  9.c.  The proposed action may be visible from publicly accessible vantage points:

  i.  Seasonally (e.g., screened by summer foliage, but visible during other
  seasons)

  ii.  Year-Round

  See response to 9.a., above.

  9.d.  The situation or activity in which viewers are engaged while viewing the
  proposed action is:

  i.  Routine travel by residents, including travel to and from work

  ii.  Recreational or tourism based activities

  See response to 9.a., above.