Village of East Aurora Water System Improvements  July 2026
SEQRA Part 3 Supporting Information

  The proposed water main replacement includes work within Hamlin Park, where
  two existing water mains will be replaced and connected to the existing
  distribution system on South Grove Street and Prospect Avenue. Construction
  activities within the park will be temporary and limited to the area necessary to
  complete the utility improvements. Upon completion of construction, disturbed
  areas within the park will be restored to pre-construction conditions. The
  proposed action will not permanently remove recreational facilities, reduce
  public access to Hamlin Park, or impair the park's recreational function.

  12.  Impacts on Critical Environmental Areas

  No impacts to Critical Environmental Areas were identified. There are no Critical
  Environmental Areas within or near the project area.

  13.  Impacts on Transportation

  13.e.  The proposed action may alter the present pattern of movement of people or
  goods.

  Water main installation will occur within the rights-of-way of multiple Village,
  Erie County, and State-owned roads. Temporary lane closures, traffic shifts, and
  minor disruptions to vehicular and pedestrian travel may occur during
  construction. The Village will obtain all applicable highway work permits for
  work within State and County rights-of-way, and traffic will be maintained in
  accordance with applicable permit requirements and traffic control measures.
  Upon completion of construction, all roadways will be restored to pre-
  construction conditions. The proposed project will not permanently alter
  roadway capacity, traffic patterns, pedestrian access, or the movement of
  people or goods.

  14.  Impacts on Energy

  The proposed project will not require the construction or expansion of electrical
  substations, transmission lines, or other energy supply infrastructure. The
  replacement hydropneumatic booster pump station will be constructed at the
  existing booster pump station site and will continue to operate using the
  existing electrical service. Rehabilitation of the existing water storage tanks and
  replacement of the water distribution system will not result in a substantial
  increase in energy demand. Accordingly, the proposed action is not expected to
  result in significant adverse impacts related to energy use.

  10