Village of East Aurora Water System Improvements  July 2026
SEQRA Part 3 Supporting Information

  2.  Impacts on Geological Features

  No impacts to geological features were identified. The proposed action will not result in
  the modification or destruction of, or inhibit access to, any unique or unusual landforms
  on the site (e.g., cliffs, dunes, minerals, fossils, caves).
  3.  Impacts on Surface Water

  3.d.  The proposed action may involve construction within or adjoining a freshwater
  or tidal wetland, or in the bed or banks of any other water body.

  Water main installation will generally occur within existing maintained areas
  and roadway rights-of-way. Several wetlands mapped by the U.S. Fish and
  Wildlife Service (USFWS) National Wetlands Inventory (NWI) are located
  adjacent to portions of the project corridor along Nye Hill Road, Sheafer
  Avenue, Church Street, North Grove Street, East Fillmore Avenue, and Lawrence
  Avenue. In addition, NYSDEC Freshwater Wetland EA-8 is located approximately
  200 feet east of Lawrence Avenue. The proposed water main replacements will
  cross several streams, including Tannery Brook at Sheafer Avenue, North Grove
  Street, Church Street, and East Fillmore Avenue. The proposed rehabilitation of
  the existing water storage tanks and replacement of the booster pump station
  will occur at existing utility facilities and are not expected to affect wetlands or
  other surface waters.

  Wetland delineations will be completed during final design to identify
  jurisdictional wetlands and other surface waters within the project area.
  Trenchless installation methods will be utilized where practicable to avoid or
  minimize impacts to wetlands and streams. Where open-cut installation is
  necessary, impacts are expected to be temporary and limited to the minimum
  area required for construction. No permanent wetland impacts are anticipated.
  Any required permits or approvals from the NYSDEC and USACE will be obtained
  prior to construction, and all work will be completed in accordance with
  applicable permit conditions. Disturbed areas will be restored following
  construction.

  3.e.  The proposed action may create turbidity in a waterbody, either from upland
  erosion, runoff, or by disturbing bottom sediments.

  Ground disturbance associated with water main installation, hydrant and gate
  valve replacement, and stream crossings has the potential to temporarily
  increase turbidity through upland erosion, stormwater runoff, or disturbance of
  bottom sediments where in-stream work is required. A SWPPP will be prepared
  and implemented to identify appropriate erosion and sediment control

  4