Item g.

CAMCO GENERAL CONTRACTING INC.  PROPOSED
  CHANGE ORDER
10994 Tinkham Road  Phone: (585)547-3898  No.  10
Darien, New York 14040  Fax: (585)547-3855

TITLE:  Unforeseen Concrete Slab  DATE:  05/28/2026

PROJECT:  HAMLIN
  TOILET ROOM ADDITION IN HAMLIN PARK

TO:  Attn: Matthew Fuller
  Barton & Loguidice, D.P.C.  ORIG: Owner Request
  11 Centre Park, Suite 203  SUBMITTED:
  Rochester, New York 14614  COMPLETED:
  Phone:(585) 325-7190
  REQUIRED:

DESCRIPTION
During excavation of the existing roadway along S Grove Street for the new sewer tie-in, a thick concrete
slab was found under the existing pavement. CamCo had to rent a hydraulic hammer for their skidsteer
to break said concrete in order to finish the excavation. This was an unforeseen condition that was not
captured in the original sewer proposal submitted via PCO-001.

Num Item  Description  Ref  Qty Unit  Unit Price  Amount
  1 024000  Skidsteer  4.000 Hrs  150.00  600.00

  2 024000  Operator Time  4.000 MH  90.00  360.00

  3 024000  Hydraulic Hammer Rental  1.000 LS  243.00  243.00

  4 100000  CamCo OH&P (20%)  1.000 LS  241.00  241.00

  Item Total:  $1,444.00
  Total:  $0.00

  Total:  $1,444.00

Exclusions:
1) CamCo proceeded with work without prior approval of costs due to time constraints and concern for
public safety.

APPROVAL

  By:  By:
  Cameron P. Sitarek

  Date:  05/28/2026  Date: