Text · page 130 of 240
Read the whole document on one page (all 240 pages, each with its own heading)
article. In making a recommendation to approve with modifications or disapprove the SWPPP, the SMO shall state the reasons for the decision in writing. If the SMO recommends to approve with modifi cations or disapprove the SWPPP, the applicant shall revise such SWPPP in accordance with the recommendations of the SMO and shall submit the rev ised SWPPP to the SMO for review. The agency or board of the Village of East Aurora reviewing the application for approval of a land development activity shall not approve such application unless the SWPPP complies with the requirements of this article. C. For all land development activities not subject to review by the Planning Board or Village Board of the Village of East Aurora as stated in§ 285-79B of this chapter, the applicant or developer shall be required to submit a SWPPP prepared in accordance with the standards contained in this article to the SMO. Within 45 days of receipt ofa SWPPP, the SMO shall approve, approve with modifications, or disapprove the SWPPP. Approval shall only be given if the SWPPP complies with the requirements of this a1ticle. In approving with modifications or disapproving the SWPPP, the SMO sha ll state the reasons for the decision in writing. In order to be approved, an applicant shall revise a SWPPP that has been approved with modifications or disapproved in accordance with the recommendations of the SMO and shall submit the revised SWPPP to the SMO for review. § 285-80. Stormwater pollution prevention plans required; contents. A. Stonnwater pollution prevention plan requirement. No application for approval of a land development activity shall be reviewed until the SMO or such agency or board of the Village of East Aurora which may be reviewing any application for approval of a land development activity requiring submission of a SWPPP has received a SWPPP prepared in accordance with the specifications in this a1ticle. B. Contents of storm water pollution prevention plans. (1) All SWPPPs shall provide the following background information and erosion and sediment controls: (a) Background information about the scope of the project, including the location, type and size of the project; (b) Site map/construction drawing(s) for the project, including a general location map. The site map should be at a scale ofno smaller than one inch to JOO feet. At a minimum, the site map should show the total site area; all improvements; areas of disturbance; areas that will not be distmbed; existing vegetation; on- site and adjacent off-site surface water(s); wetlands and drainage patterns that could be affected by the land development activity; existing and final slopes; locations of off-site material, waste, borrow or equipment storage areas; and location(s) of the stormwater discharge(s); (c) Description of the soil(s) present at the site; (d) Construction phasing plan describing the intended sequence of construction activities, including c learing and grubbing, excavation and grading, utility and infrastructme installation and any other activity at the site that results in soil disturbance. Consistent with the Erosion Control Manual, not more than five acres shall be disturbed at any one time unless pursuant to an approved SWPPP; (e) Description of the pollution prevention measmes that will be used to control litter, construction chemicals and construction debris from becoming a pollutant source in stormwater runoff; (f) Description of construction and waste materials expected to be stored on site with updates as appropriate, and a description of controls to reduce pollutants from these materials, including storage practices to minimize exposure of the materials to stormwater, and spill prevention and response; (g) Temporary and permanent structural and vegetative measmes to be used for soil stabilization, rnnoff control and sediment control for each stage of the project, from initial land clearing and grubbing to proj ect c lose-out; 7 42