Enforcement Response Plan: Post-Construction Stormwater Management Practice Inspection & Maintenance

  -
  Violation  Issue  Minimum Response

  Failure to perform required inspections and/or  i) No SMP inspection report submitted  i) Warning letter with schedule for correction (NOV
  Maintenance

  submit inspection report.  Optional)

  NYS DEC Stormwater Management Practices  ii) No inspection report submitted - violation  ii) NOV
  Inspection Checklists 2017:  continued for 30 or more days after notice
  https://www.dec.ny.gov/docs/water_pdf/smpin
  spchklist.pdf  iii) No inspection report submitted - violation  iii) Formal Enforcement/Fines
  continued for 60 or more days after notice
  Enforcement Response Plan:

  Failure to perform required maintenance as  i) SMP maintenance not performed  i) Warning letter with schedule for correction (NOV
  called for in the Maintenance Agreement  Optional)
  associated with the post-construction
  stormwater management practice(s); or, in the ii) Maintenance not performed - violation  ii) NOV
  absence of a formal Maintenance Agreement,  continued for 30 or more days after notice
  NYS DEC Maintenance Guidance for
  Stormwater Management Practices 2017:  iii) Maintenance not performed - violation  iii) Formal Enforcement/Fines
  https://extapps.dec.ny.gov/docs/water_pdf/sm continued for 60 or more days after notice
  pmaintguidance.pdf

  Failure to address deficiencies, corrective  i) Failure to correct SMP deficiencies  i) Warning letter with schedule for correction (NOV
  actions, or further investigation (if  Optional)
  recommended in inspection report)
  ii) Failure to correct deficiencies in accordance  ii) NOV
  with schedule: violation continued for 30 or more
  days after notice
  Post-Construction Stormwater Management Practice Inspection &

  iii) Failure to correct deficiencies in accordance  iii) Formal Enforcement/Fines
  with schedule: violation continued for 60 or more
  days after notice
  Appendix O (continued)

68