Water, sewer and drainage, Zoning and land use, Public safety, Budget and taxes, Parks and recreation, Roads and traffic, Audits and oversight, Moratoriums, Energy and data center siting, Short-term rentals, Housing

Original document

Same meeting

Text · page 45 of 240

Read the whole document on one page (all 240 pages, each with its own heading)

c. All sites with construction activity identified in the inventory will be inspected annually
  during active construction, after the pre-construction meeting, or sooner if deficiencies are
  noted that require attention.
  i. Follow up to construction site inspections must confirm corrective actions are
  completed within timeframes established by the CGP and the MS4 Operator’s
  Enforcement Response Plan.

  d. The names, titles, and contact information for the individuals who have received the NYSDEC
  4-Hour Erosion and Sediment Control Training are updated annually;

  e. All construction inspections are documented using the NYSDEC Construction Site Inspection
  Report Form (Appendix G) or an equivalent form containing the same information. The
  completed Construction Site Inspection Reports are considered part of the Village of East
  Aurora SWMP Plan and are available as follows:

  •  Upon request: contact Stormwater Program Coordinator or Stormwater
  Management Officer listed on page 2 of this document

  •  At the Village of East Aurora municipal building as follows:
  o Hardcopy: DPW
  o Electronically:
  • Public: Upon Request
  • Internally: C:\Users\Water Foreman\Documents\Storm
  Water\Construction Inspections

Compliance documentation is listed in Appendix B for:
  • Staff conducting construction inspections that have received NYSDEC 4-Hour Erosion and
  Sediment Control Training

9. Construction Site Close-out
  a. To close out a CGP-regulated construction site, the Village of East Aurora conducts and
  documents a final construction site inspection. The final construction site inspection is
  documented using the Construction Site Inspection Report Form (Appendix G), or an
  equivalent form containing the same information, or accept the construction site
  owner/operator’s qualified inspector final inspection certification that is required by the
  CGP. The completed (final) Construction Site Inspection Reports are considered part of the
  Village of East Aurora SWMP Plan and are available as follows:

  •  Upon request: contact Stormwater Program Coordinator or Stormwater
  Management Officer listed on page 2 of this document

  •  At the Village of East Aurora municipal building as follows:
  o Hardcopy: DPW