corrective actions identified by the qualified inspector during a site inspection.
  I also understand that the owner or operator must comply with the terms and
  conditions of the most current version of the New York State Pollutant
  Discharge Elimination System ("SPDES") general permit for stormwater
  discharges from construction activities and that it is unlawful for any person
  to cause or contribute to a violation of water quality standards. Furthermore,
  I am aware that there are significant penalties for submitting false
  information, that I do not believe to be true, including the possibility of fine
  and imprisonment for knowing violations"

  In addition to providing the certification statement above, the certification page must
  also identify the following:
  • Specific elements of the SWPPP that each contractor and subcontractor will
  be responsible for, and include the name and title of the person providing the
  signature;
  • The name and title of the trained contractor responsible for SWPPP
  implementation;
  • The name, address and telephone number of the contracting firm;
  • The address (or other identifying description) of the site; and
  • The date the certification statement is signed.
  The owner or operator of the Construction General Permit must attach the
  certification statement(s) to the copy of the SWPPP that is maintained at the
  construction site. If new or additional contractors are hired to implement measures
  identified in the SWPPP after construction has commenced, they must also sign the
  certification statement and provide the information listed above.

  d. Review the construction oversight program and expectations for compliance.

8. Construction Site Inspections
The Village of East Aurora inspects CGP-regulated construction sites to ensure they are in
compliance with the SWPPP that pertains to the site.

  a. All individual(s) responsible for construction site inspection will complete four (4) hours of
  NYSDEC endorsed training in proper erosion and sediment control principles by attending
  the NYSDEC 4-Hour Erosion and Sediment Control Training. This training is offered annually
  by Erie and Niagara County Soil and Water Conservation Districts, as well as online by other
  Soil and Water Conservation Districts across the state. This training will be completed every
  three (3) years thereafter to maintain active certification.

  b. All MS4 Construction Site Inspectors will receive this training prior to conducting
  construction site inspections.
  i. Individuals without these trainings cannot inspect construction sites.

  ii. Individuals who meet the definition of a qualified professional or qualified inspector are
  exempt from this requirement.