E. MCM 5 – Post-Construction Stormwater Management
The Village of East Aurorahas a program to ensure proper operation and maintenance of post-
construction Stormwater Management Practices (SMPs) for new or redeveloped sites. This program
is designed to promote the long-term performance of post-construction SMPs in removing
pollutants from stormwater runoff. The Village of East Aurora Post-Construction Stormwater
Management Program is supported by Local law 11-2007 Village of East Aurora, NY Stormwater
Management (ecode360.com)

1. Applicable Post-Construction SMPs
The Village of East Aurora post-construction SMP program addresses stormwater runoff to the MS4
from publicly owned/operated and privately owned/operated post-construction SMPs that meet
the following:
a. Post-construction SMPs that have been installed as part of any CGP regulated construction site or
individual SPDES permit since March 10, 2003; and

b. All new post-construction SMPs constructed as part of the construction site stormwater runoff
control program.

2. Post-Construction SMP Inventory & Inspection Tracking
The Village of East Aurora maintains an inventory of post-construction SMPs that encompasses the
entire municipality, within and beyond the MS4 regulated area.

a. The Village of East Aurora under its continuing MS4 General Permit coverage:
  i. Maintains the inventory from previous iterations of the MS4 General Permit requirement
  for post-construction SMPs installed after March 10, 2003; and

  ii. Will update the inventory for post-construction SMPs installed after March 10,
  2003 as post-construction SMPs are approved or discovered; or after an owner/operator of
  CGP-regulated construction activity has filed a NOT with the NYSDEC.

b. Annually, the Village of East Aurora updates the inventory of post-construction SMPs to include
the post-construction SMPs as noted above.

c. Within five (5) years
The following information will be included in the inventory either by using Village of East Aurora
maintenance records or by verification of maintenance records provided by the owner of the post-
construction SMP:
  i. Street address or tax parcel;

  ii. Type;

  iii. Receiving waterbody name and class;

  iv. Receiving waterbody WI/PWL Segment ID
  v. Date of installation (if available) or discovery;