4 TOWN OF HAMBURG | ENGINEERING DESIGN SERVICES CO#1 CHANGE ORDER #2 FEE: We trust the above scope of work meets your requirements. We are proposing to perform the scope of work on a Lump Sum basis. The proposed Lump Sum fee is provided below. Task Fee Task 1 – Construction Documents (Completed, --- not included) Task 2 – CO#1 Concept (Completed, not --- included) Task 3 – CO#1 Construction Plans Revisions --- (not included) Task 3.1 – CO#1 Sidewalk Heating Plans (not --- included) Task 3.2 – CO#2 Police Station Revisions $4,100 Task 4 – CO#1 NYSDOT Driveway Permitting --- (not included) TOTAL CO#2 FEE $4,100 Fee Notes: 1) Should Wendel be required to perform additional services beyond those outlined above, in Change Order #1, or the Original Contract, Wendel shall be compensated on an hourly or fixed sum basis for a mutually agreed scope of services. 26 wendelcompanies.com