May 2026 Initial Project Proposal/Final Design Report PIN 5765.54 Project Approval Sheet Milestones Signatures Dates A. Recommendation The project cost and schedule are consistent with the Regional Capital Program. for, Initiation, Scope and Design Approval: —e 5/1 froze ae J. Kinderman, P.E., Regional Planning and Program _— Date anager B. Recommendation All requirements requisite to these actions and approvals have been met, the required for Scope, independent quality control reviews separate from the functional group reviews have been Design, and accomplished, and the work is consistent with established standards, policies, regulations Nonstandard and procedures, except as otherwise noted and explained. Feature The nonstandard features have been adequately justified and it is not prudent to eliminate Approval: them as part of this project. 5/1/2026 Gerard J Sep ., senior Vice President, Engineering, Date Azar Desig C. Public Hearing A public hearing was not required. Certification (Pursuant to 23 USC 128 and 23 CFR 771.111): 5/1/2026 Gerard 1 Bp .E., Vice President, Engineering, Azar Date Design D. Local Project The required environmental determinations have been made, and the preferred Scope and alternative for this project is ready for final design. Design Approval Charles Snyder, Town of Aurora Supervisor Date CONTACT: Town of Aurora Highway Department 251 Quaker Road East Aurora, NY 14052 PHONE: (716) 652-4050 PROJECT MANAGER: David Gunner ii