C-2 Series - Grading Plans
  1. Per the site plan checklist, the minimum slope of pavement is to be 1.5%. While the majority
  of asphalt grades are close to this, and drainage is not anticipated to be a major concern as
  shown, please review grading plans to best attempt to meet this requirement within reason.
  Response: The pavement grading, especially on the north section, was largely
  constrained due to placement of the buildings and the existing grade. It is our opinion
  that the 1.2% minimum slope will be sufficient to provide proper drainage.

  2. It is assumed that two separate bioretention areas have been included in order to ensure each
  falls under the maximum contributing area threshold of 5-acres. We’d recommend to the
  applicant to further vertically separate these two bioretention areas to ensure they act
  independently from each other. Furthermore, we’d recommend the applicant review the
  potential need for rip-rap stabilization on the larger detention area’s side slopes adjacent to
  the bioretention basins to prevent erosion in the case the bioretention basins overflow.
  Response: The grading plan has been revised to note a berm is to be installed between
  the two bioretention areas to ensure that they acti independently. In the case of
  overflow, runoff will be directed to the detention area, which has been noted to be
  lined with rip-rap.

C-3 Series - Drainage Plans/ Details
  1. Please provide an outlet structure detail for the bioretention areas clearly showing the
  elevations of the proposed outlets. Maintain coordination with the HydroCAD model for these
  elevations.
  Response: An outlet structure detail has been added to Sheet C-303.

C-4 Series - Utility Plans/ Details
  1. Please provide utility profiles for all proposed Sanitary Sewers/Laterals and Water service
  lines ensuring that all utility crossings are included.
  Response: Utility profiles are shown on Sheet C-406.

  2. While it is anticipated final locations will be coordinated with and determined by the utility
  provider, please provide approximate locations for electrical and gas services.
  Response: Approximate locations for electrical and gas services have been added to the
  utility plans.

  3. Please relocate San MH-1 further to the South such that the new gravity section of sewer is
  perpendicular with the existing manhole. The proposed force main and 6” gravity sewer
  lateral form the adjacent building can be extended and routed into the manhole. This will
  improve the hydraulics of the sewage from the site entering the Town System and eliminates
  a potential conflict with existing catch basins.
  Response: SAN MH 1 has been relocated as requested.

  4. We recommend the applicant utilize fused 3” or 4” HDPE pipe instead of 3” SDR-21 PVC pipes
  as it will help eliminate bends and pipe joints which are potential points for leaks.